KUALA LUMPUR: Electrical engineering service provider HE Group Bhd recorded revenue of RM131.1 million for 9M ended Sept 30, 2026 (FY26), a 36.7% year-on-year (YoY) increase from RM95.9 million in 9M FY25.
In line with the higher topline, gross profit (GP) increased 37.2% YoY to RM26.9 million, with the GP margin sustained at 20.5%.
Profit after tax (PAT) grew 34.7% YoY to RM12.8 million from RM9.5 million.
Notably, the group’s 9M FY26 PAT has already surpassed its full-year PAT of RM11.0 million for FY25.
Revenue growth was led by the Power Distribution System segment, which grew 157.5% YoY to RM107.1 million from RM41.6 million in 9M FY25, accounting for 81.7% of total revenue.
This was followed by the Electrical Equipment Hook-Up and Retrofitting business, which generated RM14.3 million, or 10.9%, while the Other Building Systems and Works division recorded RM8.8 million, or 6.7%.
The Trading division accounted for the remaining RM0.9 million, equivalent to 0.7%.
For Q3, HE Group delivered a strong set of results, with revenue surging 81.7% YoY to RM58.7 million from RM32.3 million in Q3 FY25.
In line with the higher topline, GP grew 57.1% YoY to RM11.0 million from RM7.0 million, while PAT climbed 52.9% YoY to RM5.2 million from RM3.4 million.
The stronger performance stemmed from higher progress on ongoing projects and the commencement of new projects secured during the financial period.
Managing director Haw Chee Seng said the performance reflects the successful conversion of the group’s order book into earnings, as several major projects secured earlier in the year progressed well during the quarter.
“2026 has been a milestone year for order book replenishment. Among others, we secured two main electrical works subcontracts for data centres in Johor worth approximately RM102 million and RM124 million, respectively, an RM86 million contract to construct a 132kV/33kV substation in Selangor, and an RM25 million power distribution job for an advanced NAND flash memory facility.
“With these wins, our order book stands at approximately RM387 million as of 16 November 2026, giving us clear earnings visibility well into 2028.
“The operating landscape remains highly supportive of our business. Malaysia’s economy grew a resilient 5.3% YoY in the third quarter of 2026, while approved investments rose 11.7% YoY to RM218.5 billion in the first half of the year, with data centre and cloud computing projects accounting for approximately 44.0% of the total.
“As these investments are realised, we expect sustained demand for electrical installation and power distribution works – precisely where our expertise lies,” he added.
Beyond data centres, Haw said the continued expansion of semiconductor and electrical and electronics manufacturing, reinforced by the New Industrial Master Plan 2030 and the National Semiconductor Strategy, will drive demand for reliable, high-capacity electrical infrastructure.
Global semiconductor sales are forecast to grow 27.0% YoY in 2027, while Tenaga Nasional Bhd’s planned RM43 billion investment between 2025 and 2027 to strengthen and modernise the national grid opens further opportunities in power infrastructure.
“Looking ahead, we are confident in our growth trajectory. We will continue to pursue opportunities aligned with our expertise and execution capacity while maintaining a prudent tendering approach and disciplined project execution to safeguard margins and deliver sustainable value to our shareholders,” he said.
As of Sept 30, 2026, HE Group maintained a healthy financial position, with total cash and cash equivalents of RM53.6 million and bank borrowings of RM1.3 million.
Net assets per share strengthened to RM0.18, up from RM0.16 as of Dec 31, 2025.