Lacson seeks restoration of P8.1B in Cut DoTr FAPs

WorldPolitics
26 Nov 2026 • 9:20 PM MYT
The Manila Times
The Manila Times

One of the longest-running English broadsheets in the Philippines

Lacson seeks restoration of P8.1B in Cut DoTr FAPs

MANILA, Philippines — Sen. Panfilo "Ping" Lacson on Thursday called for the restoration of some P8.1 billion in funding for foreign-assisted projects (FAPs) under the Department of Transportation (DoTr), stressing the need to prioritize growth-oriented investments over discretionary assistance.

Lacson said the projects that suffered cuts include the Davao Public Transport Modernization Program which lost P5.1 billion, and the New Cebu International Container Port, which lost P3 billion in the budget bill.

"I hate to sound like a broken record but these are the growth-oriented investments that we must prioritize instead of ayudas," Lacson said during his interpellation of the DoTr's budget for 2027.

"These are priority not only because they entail commitment fees but because (they are) growth investments," he added.

Lacson lamented that since 2024, Congress had enacted far less funding for transportation projects than the Executive proposed.

In 2024, the Executive proposed P213.7 billion, but Congress enacted only P41.2 billion, or 19 percent of the proposed amount. In 2025, the proposed P180.9 billion was reduced to P89.8 billion (50 percent), while the proposed P197.3 billion for 2026 was trimmed to P137.8 billion (70 percent).

For 2027, the Executive proposed P299.5 billion. The House version of the budget reduced this to P259.1 billion (86 percent), but the Senate almost fully restored the allocation to P294.6 billion (98 percent).

Lacson cited the Davao Public Transport Modernization Program as an example of how funding cuts can lead to additional costs for the government.

The seven-year project started in 2023, with the loan scheduled to close in June 2030. The House version of the budget bill cut its funding for 2027 by P5.1 billion.

The government already incurred P20 million in commitment fees due to delays from December 2023 to June 2026.

Senate Finance Committee Chairman

JV Ejercito said the penalties may amount to P3 million a year.

Lacson said that if the project does not start in 2027, "definitely we will have penalties to pay," adding that the Senate can restore the P5.1 billion only with the imprimatur of Ejercito as finance committee chairman.

"Yes, anything for infrastructure. If we have a source (of funds) I would also want to restore... These are projects that will have economic impact," Ejercito replied.