LCS project 7.55 pct behind schedule

KUALA LUMPUR, Oct 5 - The Littoral Combat Ship (LCS) project was 7.55 per cent behind schedule as of June 25, 2026, with delays ranging from 30 to 108 days, the National Audit Department (JAN) said.

The delay posed a risk to the Physical Handover (PHO) of LCS 1, initially scheduled for August 26, 2026, and the revised target of December 26, 2026.

“Should the PHO take place on either date, LCS 1 will be handed over without full operational capability, as training and weapon systems have yet to be completed.

“Full operational readiness of the LCS project depends on the Supplementary Contract, which can only be completed in December 2035, well beyond the Main Contract’s deadline of April 25, 2030. The delay in the PHO of LCS 1 will also affect the PHO timelines for LCS 2 through LCS 5,” it said in a statement on the Auditor General’s Report (LKAN) 2/2026.

The Auditor General’s Report (LKAN) 2/2026, covering the federal government’s Financial Statements for 2025, the activities of federal ministries and departments, as well as state governments, agencies, ministries and departments and the management of state-owned companies, was tabled in the Dewan Rakyat today.

JAN said it conducted an interim audit to assess the management of the LCS Project, including its physical and financial progress, contract management, and payments, based on the terms of the contract and regulations in force.

The audit took into account a recommendation by the Public Accounts Committee (PAC) in its Parliamentary report dated October 9, 2023, urging JAN to audit the LCS Project before handing over LCS 1 to the Royal Malaysian Navy (TLDM) and table the findings in Parliament.

To ensure the LCS Project is completed and handed over with the required level of operational readiness, JAN recommended that the Defence Ministry (MINDEF) establish a realistic recovery action plan, with all critical activities under the Main Contract and Supplementary Contracts aligned with the LCS PHO schedule.

It also recommended that MINDEF ensure any conditional acceptance of the vessels clearly sets out the contractor’s obligations, completion timelines, and responsibilities until the vessels achieve the specified operational capabilities.

JAN similarly recommended that the ministry strengthen project monitoring by assigning responsible officers and setting deadlines to resolve each critical issue until the project is completed.