MANILA, Philippines — The government is targeting a less-than-one-hour train journey between Makati City and Clark International Airport by the end of 2029 through a railway connection expected to make flights from Clark more accessible to Metro Manila passengers and help ease congestion at the Ninoy Aquino International Airport (NAIA).
Department of Transportation (DOTr) Secretary Vince Dizon on Tuesday said that the over 147-kilometer North-South Commuter Railway (NSCR) would provide direct rail service between Makati City and Clark in Pampanga with only three stops along the route.
It (NSCR) connects Metro Manila, Central Luzon and Calabarzon (Cavite, Laguna, Batangas, Rizal and Quezon), spanning 22 local government units across these three regions with 35 to 36 stations.
The connection would give travelers an alternative to road transportation, allowing them to reach Clark without having to drive or take a bus from Metro Manila, according to the agency.
"Less than one hour from Makati to Clark International Airport," said Dizon who inspected the Clark airport station.
The DOTr chief said the railway would encourage more passengers to consider flying from Clark, which also serves travelers from Central and Northern Luzon.
Clark's potential catchment area includes Bulacan, Pampanga, Tarlac, Zambales, Bataan and Pangasinan, whose residents would have an alternative airport without having to travel to Metro Manila first, he said.
The DOTr said it was targeting completion of the Clark airport station by the end of 2027. The station will be connected to the airport terminal through a 300-meter walkway equipped with travelators, allowing passengers to reach the terminal in about seven minutes.
Dizon said train testing could begin by the end of 2027 or early 2028.
While the full Makati-to-Clark connection is targeted for completion by the end of 2029, the department was also working to begin operations on the Valenzuela-Malolos section in the first quarter of 2028, according to the top DOTr official.
Travel time between Valenzuela and Malolos, which currently takes about one-and-a-half to two hours by road, was expected to fall to around 40 minutes by train, he said.
Admitting that the railway project had suffered years of delays, dating back to the NorthRail project in the 1990s, Dizon said the department was now working to meet its revised construction schedule.
"I cannot bring back the past. We just have to move forward," he said, adding that the timelines he presented were currently on schedule.
Right-of-way acquisition is no longer a problem for the Clark airport station package, Dizon said, although issues remained along other sections.
The NSCR's construction from Valenzuela to Clark currently employs about 10,000 workers, the transportation department said.
Once operational, the railway is expected to generate another 3,000 to 4,000 jobs, including positions for train drivers and personnel managing railway facilities, it added.
The DOTr expects to award the railway's operations and maintenance contract by February 2027, allowing the winning operator to begin hiring and training personnel.