PAC probe must include termination of delivery model

LocalPolitics
16 Nov 2026 • 8:34 AM MYT
Daily Express
Daily Express

Daily Express Online (Malaysia) is Sabah's top-ranked & most viewed English news site. It is also Sabah's leading & most circulated daily English newspaper.

PAC probe must include termination of delivery model

PAPAR: The Public Accounts Committee (PAC) has been urged to expand its probe into the Sabah Pan Borneo Highway project by including the rationale and implications of terminating the Project Delivery Partner (PDP) model in 2019.

Gabungan Rakyat Sabah (GRS) Sec-Gen. Datuk Armizan Mohd Ali said this is to determine whether this decision was what contributed to delays in the Pan Borneo project’s implementation.

He said seven GRS Members of Parliament including himself as the Papar MP would submit an official Memorandum to PAC, next week.

“The PAC investigation is not intended to find fault with any party, but to ensure that government policy decisions are not influenced by political interests to the extent of disrupting the progress of infrastructure projects needed by the people.

“We do not want a situation where, whenever there is a change of government, the first thing done is to look for faults, cancel or postpone projects, leaving the people to bear the consequences.

This is an important lesson to ensure that the people’s interests and continuity of infrastructure development always remain the priority,” he said.

Armizan said the call followed the Auditor-General’s Report (AG’s Report) Series 2/2026 on the project which had triggered controversy and exchanges of accusations among various parties.

“It is hoped that the PAC investigation will be conducted comprehensively and transparently to identify the actual causes of the delays and ensure that all parties involved in the decisions and implementation of the project provide the necessary explanations.

“In this regard, it is proposed that the scope of the PAC investigation should also cover the rationale behind and implications of terminating the PDP model for the implementation of the Pan Borneo Highway Phase 1A on Sept 22, 2019, following changes in the State and Federal Government administrations,” he said.

Armizan said this in a press conference after the closing ceremony of the IP (Intellectual Property) SPARK programme at SMK Pengalat, Sunday.

I Sabah Pan Borneo Phase 1 comprises 35 packages, which consists of Phase 1A for 16 packages and Phase 1B for 19 packages.

Construction of Phase 1 began on April 11, 2016, covering a total distance of 706km from Sindumin to Kota Kinabalu and Kudat; Ranau to Batu 32 Sandakan; and Batu 32 Sandakan to Tawau.

Previously, the PAC was reported to be investigating the implementation of the Sabah Pan Borneo Highway project, particularly Phase 1A, following findings in the AG’s Report Series 2/2026, which highlighted delays and implementation issues.

The investigation is expected to examine various aspects of the project’s progress, including factors contributing to delays in the respective work packages.

The 2026 AG’s Report Series 2 revealed that only four of the project’s 35 work packages, or 11.4 per cent, had been completed as at March 31, while the remaining 31 packages, worth RM16.3 billion, were still under implementation.

The report noted that this was despite the management of the highway construction project having been transferred from the PDP to the Ministry of Works on September 22, 2019.

Armizan said GRS welcomed the PAC’s decision to investigate the project’s implementation but believed the scope should be expanded to cover four key aspects relating to the termination of the PDP model.

“Firstly, the AG’s Report Series 2/2026 do not clearly explain the issue surrounding the termination of the PDP model, although official responses by the Ministry of Works (KKR) in the Dewan Rakyat on August 2, 2022, and October 19, 2026, by former Works Minister Datuk Seri Arthur Joseph Kurup and Deputy Works Minister Datuk Seri Dr Ahmad Masan, respectively, explicitly identified the termination of the PDP model as one of the main factors contributing to delays in the Pan Borneo Highway Phase 1A project.

“This is not a political narrative, but an official government response in Parliament that deserves attention,” he said.

Secondly, Armizan said what needed to be investigated is the rationale and circumstances surrounding the termination of the PDP model in 2019 should be clarified, particularly as the decision was made by the then Federal Government following a recommendation from the newly-formed Sabah State Government administration at that time.

“The public had the right to know the actual reasons behind the decision and the considerations that prompted the government to change the project’s implementation model,” he said.

Thirdly, Armizan said, concerned uncertainty over the status of the PDP arrangement and contractors following the change of government in May 2018, which allegedly disrupted construction works at project sites under Phase 1A that was stalled for more than a year.

“At the same time, delays in the process of reappointing contractors through the conventional procurement method also affected implementation costs due to rising construction material prices and inflation, before the project subsequently faced the challenges of the Covid-19 pandemic,” he said.

Fourthly, PAC also need to look into the termination of the PDP model that caused the transition to the conventional procurement method that had disrupted the process of reappointing existing contractors and appointing new contractors for the Phase 1A packages, with the process extended until 2021.

“This fourth aspect concerns the appointment of contractors. We know that contractors were initially appointed by the PDP which began around 2017. In 2018, there was a change of government, which disrupted their work.

“Towards the end of 2019, some contractors were reappointed, but not all packages were covered. While some existing contractors for Phase 1A packages were reappointed, the appointments for the remaining packages were delayed until 2021 due to the change in government.

“This is believed to be one of the contributing factors to the delays. It is important to understand that the delays being discussed involve Pan Borneo Phase 1A, whose progress is now understood to have reached nearly 90 per cent,” he said.

Another issue that was unclear in the Auditor-General’s Report (AG’s Report), he said was the apparent grouping of Phase 1A and Phase 1B packages, despite the fact that they are two separate phases.

“Some Phase 1B packages involved newly appointed contractors, with some appointments even taking place this year.

“Therefore, the two phases must be viewed separately. Phase 1A has experienced delays but its progress has now reached nearly 90 per cent, while Phase 1B appears to be progressing better as it has not faced similar disruptions or interference that could affect its implementation. Its progress has already exceeded 30 per cent,” he added.

Armizan, who is also Domestic Trade and Cost of Living Minister, suggested that the PAC also call contractors affected by the transition to provide a clearer picture of the problems and pressures they faced during the change in the project’s implementation model.

“Rather than calling only government agencies, the contractors involved should also be given the opportunity to explain what happened, including disruptions to construction works, difficulties in obtaining materials and increased costs following their reappointment.