Kota Kinabalu: Parti Kerjasama Anak Negeri calls for immediate independent quality audits and a legally binding completion timeline for the Pan Borneo Highway Sabah project.
It also warn that glaring gaps between official progress figures and dangerous on-ground realities can no longer be ignored.
The party’s president Datuk Henrynus Amin and deputy president Tsen Kim Fatt separately raised alarm over what they describe as substandard work and years of missed deadlines particularly along the critical Tebobon–Berungis stretch in Tuaran.
“Officially, the project is 90 per cent complete.
“But anyone who drives through Tebobon–Berungis will tell you it feels closer to 60 per cent and what has been done is already falling apart,” Tsen said.
“If a road starts deteriorating before it’s even officially completed, something is fundamentally wrong.
“Commuters deserve seamless, durable, high-standard infrastructure and not patchwork fixes and shifting deadlines, said Henrynus.
Both leaders highlighted the same critical concerns from site inspections and public feedback:Old roads, fresh asphalt? Several sections appear to be worn-out roads simply resurfaced rather than properly rebuilt from the foundation up — raising serious questions about long-term durability.Premature deterioration: Newly paved stretches already show uneven surfaces and patching, suggesting poor compaction or asphalt laid outside proper temperature standards.Hazardous traffic management: Misplaced concrete barriers, abrupt lane merges, poor lighting and unclear signage force motorists into dangerous daily situations.Unfinished drainage, dangerous pooling: Exposed drains and unlined culverts turn lanes into pools during rain, creating aquaplaning risks that accelerate road damage and endanger lives.The frustration is compounded by the project’s shifting timeline. Phase 1 began in 2015 with an original completion target of December 2021. That deadline has now slipped repeatedly — pushed back to mid-2028.
“Seven years of extensions is far too long. This isn’t just an inconvenience and it’s higher vehicle maintenance costs, wasted hours stuck in traffic, and real safety risks for everyone travelling between Tawau, Sandakan, Ranau, Kudat and Kota Kinabalu,” Henrynus said.
The local-base party is now urging Works Minister Datuk Seri Dr. Joachim Gunsalam to take four immediate steps: Conduct unannounced physical inspections along the Tebobon–Berungis stretch Order independent quality audits of completed and ongoing works Enforce a binding, non-negotiable completion date with clear penalties for delays Disclose the total amount paid to date and confirm sufficient funds are secured to finish the project properly.