Tony Pua & Lim Guan Eng Say LRT3 Was Never Halted Under Pakatan Harapan, Cost Cuts Saved RM9.72 Billion

LocalPolitics
2 Jul 2026 • 6:14 PM MYT
WORLD OF BUZZ
WORLD OF BUZZ

#1 social news site in M'sia that delivers you the latest & trending news from politics, entertainment, life, and more.

Tony Pua & Lim Guan Eng Say LRT3 Was Never Halted Under Pakatan Harapan, Cost Cuts Saved RM9.72 Billion

The post Tony Pua & Lim Guan Eng Say LRT3 Was Never Halted Under Pakatan Harapan, Cost Cuts Saved RM9.72 Billion appeared first on WORLD OF BUZZ.

Former Finance Minister Lim Guan Eng and former Damansara MP Tony Pua have defended Pakatan Harapan’s (PH) handling of the LRT3 project, insisting the Shah Alam LRT Line was never halted during the coalition’s administration and that its cost rationalisation saved taxpayers RM9.72 billion.

In a joint statement responding to remarks by the Sultan of Selangor, Sultan Sharafuddin Idris Shah, the pair said PH fully supported the project after taking office in 2018, describing it as a critical public transport initiative for Klang Valley residents.

IMG 20260702 092356

Cost review triggered after budget escalation

According to them, the previous Barisan Nasional administration approved RM9 billion for the project in 2015 and provided Prasarana with a RM10 billion government guarantee. However, by March 2018, Work Package Contracts worth RM15.2 billion had already been awarded.

“After accounting for land acquisition, consultancy fees, Project Delivery Partner (PDP) fees, and financing costs, Prasarana sought to increase the project’s total budget to RM31.65 billion, along with an additional RM22 billion in government guarantees.”

473111283 1137653304389449 5357599490997215501 n

722637173 1001257192380373 5426094060051757714 n

When PH took over in May 2018, construction continued without interruption while the government worked with appointed PDP MRCB-George Kent to reduce overall costs.

With the project only about 9% complete at the time, the government appointed independent engineering consultants to review the project.

“The review aimed to ensure accountability and to align the project’s scale with projected passenger demand, as approved by the Land Public Transport Commission (APAD).”

Following the review, the Cabinet approved a 47% reduction in the project’s estimated cost, bringing it down from RM31.65 billion to RM16.63 billion.

Train sets were reduced based on passenger demand forecasts

Among the cost-saving measures were reducing the train order from 42 six-car train sets to 22 three-car train sets based on passenger demand forecasts, as well as deferring the construction of five stations with initially low projected ridership. Technical provisions were retained to allow the stations to be built in the future.

The project completion deadline was also extended from 2020 to 2024, which they said avoided costly acceleration payments to contractors.

IMG 20260701 210403

Those five stations have since been reinstated under a RM5.3 billion second-phase contract that also includes additional trains and upgrades, bringing the final project cost to RM21.93 billion.

“This remains RM9.72 billion lower than the RM31.65 billion budget previously approved,” Tony pointed out.

According to the duo, the lower project cost is also expected to save the government up to RM10 billion in interest payments over the next 25 to 30 years.

They stressed that the savings did not come at the expense of passenger capacity or the rail line’s functionality. Instead, they said the funds saved could be redirected towards welfare programmes and development projects.

They concluded by thanking Sultan Sharafuddin for highlighting the importance of the LRT3 project, saying the completed line will help reduce congestion, shorten travel times and support Selangor’s economic growth.

 

Also read: MBSA Says Upgrades Underway Following Complaints Over Lack of Walkways at LRT3 Shah Alam Stations

Collage 3

Source: WOBSource: Tony Pua | FacebookSource: Lim Guan Eng | FacebookSource: WOB

The post Tony Pua & Lim Guan Eng Say LRT3 Was Never Halted Under Pakatan Harapan, Cost Cuts Saved RM9.72 Billion appeared first on WORLD OF BUZZ.

Newswav Malaysia Best News App

Newswav is an online content aggregator and obtains its content from different online sources. The content in the app do not belong to Newswav nor do they reflect the opinions of Newswav and its staff. Your use of this app indicates your understanding and acceptance of this information.

Newswav Sdn. Bhd. (201701008480 (1222645-M)) 2026 All Rights Reserved