DELAYED for nearly five decades, the Mindanao Ave. Extension project is finally nearing completion, with the Department of Public Works and Highways (DPWH) targeting its full opening in early 2027.
Public Works Secretary Giovanni Lopez on Monday said portions of the road will initially open in December.
Lopez said the accelerated completion follows President Ferdinand Marcos Jr.’s directive to finish the long-delayed project so motorists and commuters can finally benefit from the extended road network.
He made the assurance after inspecting the project to address persistent right-of-way (ROW) problems that have hampered its completion.
"With the decades-long delay, we wanted to determine whether the DPWH can finally overcome the ROW problems. The public needs more than another site inspection; it needs a definite completion timetable," he said.
The Mindanao Ave. Extension will connect portions of Quezon City, Valenzuela City and northern Caloocan, improving access to the North Luzon Expressway (NLEX) and providing motorists with an alternative route to heavily congested roads in the area.
Construction began in the 1980s but repeatedly stalled because of ROW difficulties.
Only about 1.4 kilometers of the road had been completed and opened between 1980 and 2014.
Construction resumed in 2017, with the DPWH working alongside the National Housing Authority (NHA) and local government units to resolve land acquisition and relocation issues involving informal settler families living along the proposed alignment.
In 2018, the DPWH opened an additional 700-meter section from P. Dela Cruz Street in Caloocan to MGM Road in Valenzuela.
The original 3.2-kilometer extension will have eight lanes, drainage facilities, slope protection, street lighting, sidewalks and a center island.
In 2024, portions of the extension in Caloocan were reported open to light vehicles, although restrictions remained in place against trucks and illegal parking along the road.
The DPWH has yet to provide updated figures on the project’s overall accomplishment rate, remaining ROW requirements and revised completion target.
Tokwing Construction Corp. was identified as the contractor for the Mindanao Avenue Extension Segment 2C, Phases I and II. The company completed an additional 700-meter section connecting P. Dela Cruz Street to MGM Road in Valenzuela City in April 2018.
The contract for Segment 2C was approximately P118 million. In its 2019 third-quarter report, DPWH’s Constructors Performance Evaluation System listed Tokwing Construction’s contract as approximately P68.978 million.