Works on Tawau dam resume

15 Mar 2023 • 11:50 AM MYT
Daily Express
Daily Express

Daily Express Online (Malaysia) is Sabah's top-ranked & most viewed English news site. It is also Sabah's leading & most circulated daily English newspaper.

image is not available

TAWAU: The delay in completing the Cinta Mata Water Dam Project at Gudang Empat here is due to the Covid-19 pandemic which had caused the supply of skilled labour from China to be disrupted, said Deputy Chief Minister Datuk Ir Shahelmey Yahya.

Shahelmey, who is also Public Works Minister, said the manpower required are now available and have restarted the stalled works.

The most-awaited project by the people of Tawau is expected to be completed within three years from now.