Kuala Lumpur: Tuaran Member of Parliament Datuk Seri Wilfred Madius Tangau (pic) has urged the Works Ministry to prepare a clear recovery plan for every delayed Pan Borneo Highway package in Sabah.
Debating the 2027 Budget for the Ministry at the committee stage in the Dewan Rakyat on Monday, he said the people have endured prolonged construction-related difficulties for too long and deserve to know the actual causes behind the delays.
Madius noted that land acquisition, utility relocation and contractor performance are among the recurring issues cited, questioning why land and utility problems persist after construction has started and whether contractors possess sufficient manpower, machinery and materials at ready sites.
To address the delays systematically, he proposed that each problematic package be given a recovery plan detailing the obstacles faced, responsible parties, resolution dates and completion targets, alongside written explanations for every extension of time (EOT), particularly for packages passing through Tuaran.
The Tamparuli Assemblyman and Upko Honorary President stressed that prolonged delays affect daily commuting and local economic activities, adding that implementation issues must be followed by solutions with clear timelines and accountability rather than mere explanations.